AmarnepalNepal Data
OperationalCommissioned 2019

Lower Hewa Khola Hydropower Projectतल्लो हेवा खोला

A 22.1 MW run-of-river plant in Panchthar drawing on the Hewa and Pheme kholas, developed by Mountain Hydro Nepal Ltd (listed on NEPSE). It began generating in 2019.

Installed capacity

22 MW

Run-of-river

River / basin

Hewa Khola

Koshi basin

Location

Panchthar

Koshi

Commissioned

2019

Operational

How it was built

Milestones to commissioning

The route from construction to commercial operation.

  1. 6 Aug 2019

    Commercial operation began

On the map

Location

Approximate dam-area location on OpenStreetMap — precise to the district and river reach, not the exact structure.

Loading map…
Filter by stageTiles © OpenStreetMap contributors
Questions

Lower Hewa Khola Hydropower Project: key facts

Quick answers on capacity, river, developer, status and commissioning, drawn from the sourced data above.

What is the capacity of the Lower Hewa Khola Hydropower Project?+

The Lower Hewa Khola Hydropower Project has an installed capacity of 22 MW. It is a run-of-river hydropower scheme.

Which river is the Lower Hewa Khola Hydropower Project on?+

The project is on the Hewa Khola River, part of Nepal's Koshi basin, in Panchthar district, Koshi Province.

Who is developing the Lower Hewa Khola Hydropower Project?+

The Lower Hewa Khola Hydropower Project is developed by Mountain Hydro Nepal Ltd (private (ipp)).

What is the status of the Lower Hewa Khola Hydropower Project?+

As of mid-2026 the project is operational.

When was the Lower Hewa Khola Hydropower Project commissioned?+

The Lower Hewa Khola Hydropower Project was commissioned in 2019.

Sources & data note

Figures for Lower Hewa Khola Hydropower Project are compiled from the sources below and cross-checked where possible. Status and projected dates reflect research as of mid-2026 and may change as the project progresses. The map location is an approximate dam-area estimate. Commentary is Amarnepal's own.