AmarnepalNepal Data
OperationalCommissioned 2012

Daraundi A Hydropower Plantदरौंदी ए

A 6 MW run-of-river plant on the Daraundi River in Gorkha, operated by Daraundi Kalika Hydropower. Commissioned around 2012.

Installed capacity

6 MW

Run-of-river

River / basin

Daraundi Khola

Gandaki basin

Location

Gorkha

Gandaki

Commissioned

2012

Operational

How it was built

Milestones to commissioning

The route from construction to commercial operation.

  1. 2012

    Commissioned (2069 BS)

On the map

Location

Approximate dam-area location on OpenStreetMap — precise to the district and river reach, not the exact structure.

Loading map…
Filter by stageTiles © OpenStreetMap contributors
Questions

Daraundi A Hydropower Plant: key facts

Quick answers on capacity, river, developer, status and commissioning, drawn from the sourced data above.

What is the capacity of the Daraundi A Hydropower Plant?+

The Daraundi A Hydropower Plant has an installed capacity of 6 MW. It is a run-of-river hydropower scheme.

Which river is the Daraundi A Hydropower Plant on?+

The project is on the Daraundi Khola River, part of Nepal's Gandaki basin, in Gorkha district, Gandaki Province.

Who is developing the Daraundi A Hydropower Plant?+

The Daraundi A Hydropower Plant is developed by Daraundi Kalika Hydropower Co. (private (ipp)).

What is the status of the Daraundi A Hydropower Plant?+

As of mid-2026 the project is operational.

When was the Daraundi A Hydropower Plant commissioned?+

The Daraundi A Hydropower Plant was commissioned in 2012.

Sources & data note

Figures for Daraundi A Hydropower Plant are compiled from the sources below and cross-checked where possible. Status and projected dates reflect research as of mid-2026 and may change as the project progresses. The map location is an approximate dam-area estimate. Commentary is Amarnepal's own.