AmarnepalNepal Data
OperationalCommissioned 2019

Kabeli B1 Hydropower Stationकबेली बी१

A 25 MW run-of-river plant on the Kabeli Khola (a Tamor tributary) in Panchthar/Taplejung, developed by Arun Kabeli Power Ltd, in commercial operation since 9 November 2019. (The separate 37.6 MW Kabeli-A project remains under development.)

Installed capacity

25 MW

Run-of-river

River / basin

Kabeli Khola

Koshi basin

Location

Panchthar

Koshi

Commissioned

2019

Operational

How it was built

Milestones to commissioning

The route from construction to commercial operation.

  1. 9 Nov 2019

    Commercial operation

On the map

Location

Approximate dam-area location on OpenStreetMap — precise to the district and river reach, not the exact structure.

Loading map…
Filter by stageTiles © OpenStreetMap contributors
Questions

Kabeli B1 Hydropower Station: key facts

Quick answers on capacity, river, developer, status and commissioning, drawn from the sourced data above.

What is the capacity of the Kabeli B1 Hydropower Station?+

The Kabeli B1 Hydropower Station has an installed capacity of 25 MW. It is a run-of-river hydropower scheme.

Which river is the Kabeli B1 Hydropower Station on?+

The project is on the Kabeli Khola River, part of Nepal's Koshi basin, in Panchthar district, Koshi Province.

Who is developing the Kabeli B1 Hydropower Station?+

The Kabeli B1 Hydropower Station is developed by Arun Kabeli Power Ltd (private (ipp)).

What is the status of the Kabeli B1 Hydropower Station?+

As of mid-2026 the project is operational.

When was the Kabeli B1 Hydropower Station commissioned?+

The Kabeli B1 Hydropower Station was commissioned in 2019.

Sources & data note

Figures for Kabeli B1 Hydropower Station are compiled from the sources below and cross-checked where possible. Status and projected dates reflect research as of mid-2026 and may change as the project progresses. The map location is an approximate dam-area estimate. Commentary is Amarnepal's own.