AmarnepalNepal Data
OperationalCommissioned 2021

Nyadi Hydropower Projectन्यादी

A 30 MW run-of-river plant on the Nyadi Khola (a Marsyangdi tributary) at Bahundanda, Lamjung, developed by Nyadi Hydropower Ltd — a joint venture of Butwal Power Company and Lamjung Electricity Development Co. It entered operation in the early 2020s.

Installed capacity

30 MW

Run-of-river

River / basin

Nyadi Khola

Gandaki basin

Location

Lamjung

Gandaki

Commissioned

2021

Operational

How it was built

Milestones to commissioning

The route from construction to commercial operation.

  1. 2017

    Construction commenced

  2. 2021

    Commercial operation (approx.)

On the map

Location

Approximate dam-area location on OpenStreetMap — precise to the district and river reach, not the exact structure.

Loading map…
Filter by stageTiles © OpenStreetMap contributors
Questions

Nyadi Hydropower Project: key facts

Quick answers on capacity, river, developer, status and commissioning, drawn from the sourced data above.

What is the capacity of the Nyadi Hydropower Project?+

The Nyadi Hydropower Project has an installed capacity of 30 MW. It is a run-of-river hydropower scheme.

Which river is the Nyadi Hydropower Project on?+

The project is on the Nyadi Khola River, part of Nepal's Gandaki basin, in Lamjung district, Gandaki Province.

Who is developing the Nyadi Hydropower Project?+

The Nyadi Hydropower Project is developed by Nyadi Hydropower Ltd (BPC / LEDCO) (joint venture).

What is the status of the Nyadi Hydropower Project?+

As of mid-2026 the project is operational.

When was the Nyadi Hydropower Project commissioned?+

The Nyadi Hydropower Project was commissioned in 2021.

Sources & data note

Figures for Nyadi Hydropower Project are compiled from the sources below and cross-checked where possible. Status and projected dates reflect research as of mid-2026 and may change as the project progresses. The map location is an approximate dam-area estimate. Commentary is Amarnepal's own.