AmarnepalNepal Data
OperationalCommissioned 2017

Thapa Khola Hydropower Projectथापा खोला

An 11.2 MW run-of-river plant on the Thapa Khola in Mustang, a Kali Gandaki tributary, developed by Mount Kailash Energy Co. Ltd — one of the higher-altitude plants in Nepal's grid.

Installed capacity

11 MW

Run-of-river

River / basin

Thapa Khola (Kali Gandaki)

Gandaki basin

Location

Mustang

Gandaki

Commissioned

2017

Operational

How it was built

Milestones to commissioning

The route from construction to commercial operation.

  1. Dec 2017

    Commercial operation began (2074-08-22 BS)

On the map

Location

Approximate dam-area location on OpenStreetMap — precise to the district and river reach, not the exact structure.

Loading map…
Filter by stageTiles © OpenStreetMap contributors
Questions

Thapa Khola Hydropower Project: key facts

Quick answers on capacity, river, developer, status and commissioning, drawn from the sourced data above.

What is the capacity of the Thapa Khola Hydropower Project?+

The Thapa Khola Hydropower Project has an installed capacity of 11 MW. It is a run-of-river hydropower scheme.

Which river is the Thapa Khola Hydropower Project on?+

The project is on the Thapa Khola (Kali Gandaki) River, part of Nepal's Gandaki basin, in Mustang district, Gandaki Province.

Who is developing the Thapa Khola Hydropower Project?+

The Thapa Khola Hydropower Project is developed by Mount Kailash Energy Co. Ltd (private (ipp)).

What is the status of the Thapa Khola Hydropower Project?+

As of mid-2026 the project is operational.

When was the Thapa Khola Hydropower Project commissioned?+

The Thapa Khola Hydropower Project was commissioned in 2017.

Sources & data note

Figures for Thapa Khola Hydropower Project are compiled from the sources below and cross-checked where possible. Status and projected dates reflect research as of mid-2026 and may change as the project progresses. The map location is an approximate dam-area estimate. Commentary is Amarnepal's own.